Location: Silver Lake, CT
Project Completion Date: August 2014
Client: Connecticut Department of Energy & Environmental Protection
Carylon Operating Company: Mobile Dredging & Video Pipe
MDVP hydraulically dredged 150,000 cubic yards of sediment from Silver Lake. Sediment was pumped approximately 6,400 feet to a CDF. Effluent from the CDF was treated with a polymer to achieve strict lake water quality standards.